Street Work Schedule Change

Written by Theresa Rose on April 16, 2019

Mt Pleasant Utilities and Drish Construction are installing the new water main on the East side of Main St. between Monroe and Madison. The north bound lane of Main Street is closed to traffic and traffic will only be able to travel south bound between Monroe St. and Main St. Please be cautious in the area because of the added construction on the building located on the West side of Main St. also taking place. This change in schedule is due to a delay in the delivery of materials for the new water main to be installed on South Jefferson between Clay & Washington. The installation of the water main should be completed by the end of this week. Once the main is installed crews will move back to Monroe St. and begin installing new water services from Jefferson St. to Main St.