Sewer Lining Work Continues

Written by Theresa Rose on April 15, 2019

Municipal Pipe and Tool will be working on lining on Henry St.in Mount Pleasant. Monday April 15th they will be lining in the morning from N. Poplar St. to Jay St. Then in the afternoon they will still be on Henry St. from North Jay St. to North Hamlin St.

On Tuesday April 16th the lining crew will be lining on Warren St. from S. Jay St. to Walnut St. On Wednesday April 17th lining crew will line the Alley South of Monroe St. between Adams St. & Harrison St.

Then on Thursday April 18th the lining crew will be lining in the Alley South of Monroe St. between Jackson St. & Jefferson St. Then on Friday April 19th the lining crew will be lining in the Alley South from the E. Henry St. & Lincoln St. Intersection South to Madison St.

At some point during the week the crew might work in the section along the North Side of Monroe St. from Harrison St. to Locust St. This is depending on when the Mt Pleasant Utilities can get a PP relocated and Hagerty Earthworks excavates the pipe at the Locust St. Location.

The lining is moving along very well with 80% complete.