Mt. Pleasant Mapleaf Drive Update

Written by Theresa Rose on September 4, 2016

Everything going well on Mapleleaf Drive and Crews are still on schedule to open phase 2 by Monday September 12th to allow access for the Burlington Northern Junction, Lomont Molding and Walmart Distribution Employee parking lot from Grand Ave. At that time access on Mapleleaf Drive from Iris Street will be shutoff. At that time the only section that will be shut down will be the section between Lomont Moldings Office driveway to Iris St. This will be the final phase of this project.