Mount Pleasant Street Project Update

Kinney & Sons has finished installation of the drainage structures and piping crossing Aldrin Drive. Aldrin will remain closed to through traffic over this weekend April 8th & April 9th. It is accessible to the mid-point of the street from the South off Vine St. and off Armstrong Court for the North half. It was decided to wait until after Easter weekend to start removing the pavement.

All residents should be able to access their driveways until Monday April 10th. The street will be closed to all traffic from Vine Street to Armstrong Court at approximately 7:30 A.M. The City will be picking up garbage first thing that morning. The plan is to get all concrete removed, street graded, subdrain installed and subbase material placed by Friday April 14th. Then the street would be reopened to local traffic for homeowners to access their driveways. This will continue until Jones Contracting starts setting up to trim the subbase rock for paving.